Q1.Bid evaluation must be made against:
Medium
A
The criteria stated in the bidding documents
B
New criteria after opening
C
Personal preference
D
A media survey
Contract Award PPSC
2024
Correct Answer: A
Changing criteria after bid opening undermines fairness and transparency.
Q2.The successful bidder is generally the one whose bid is:
Medium
A
Responsive and evaluated according to the stated criteria
B
The most expensive without review
C
Submitted after the deadline
D
Missing required documents
Contract Award PPSC
2024
Correct Answer: A
Award follows responsiveness and evaluation under the stated criteria.
Q3.A contract should be awarded only after:
Easy
A
Required evaluation and approval
B
A verbal suggestion
C
A supplier’s advertisement
D
The contract is completed
Contract Award PPSC
2024
Correct Answer: A
Award follows evaluation and the required approval process.