Q1.The Public Procurement Rules, 2004 apply to procurement by:

Easy
A Public sector agencies covered by the Rules
B Private households
C Foreign tourists
D Sports clubs only
Procurement Principles PPSC 2024

Correct Answer: A

The Rules regulate procurement by the public agencies to which they apply.

Q2.The primary objective of public procurement is to obtain:

Easy
A Value for money
B The highest possible price
C A private favour
D An unrecorded purchase
Procurement Principles PPSC 2024

Correct Answer: A

Public procurement seeks value for money through fair competition and transparency.

Q3.Open competitive bidding promotes:

Easy
A Fair competition
B Secret selection
C Personal preference
D Unrecorded contracts
Open Competitive Bidding PPSC 2024

Correct Answer: A

Open competition gives eligible suppliers a fair opportunity.

Q4.Procurement planning should be based on:

Easy
A Identified needs and available resources
B Random purchases
C Supplier demands only
D Personal shopping lists
Procurement Planning PPSC 2024

Correct Answer: A

Planning links procurement needs to resources and organizational objectives.

Q5.A procuring agency should avoid splitting a procurement to:

Medium
A Evade the applicable approval or procurement procedure
B Improve transparency
C Improve record keeping
D Meet a genuine technical need
Procurement Planning PPSC 2024

Correct Answer: A

Artificial splitting to avoid rules is prohibited procurement practice.

Q6.Bidding documents should clearly state:

Easy
A The requirements and evaluation criteria
B Only the supplier’s address
C No specifications
D A private agreement
Bid Evaluation PPSC 2024

Correct Answer: A

Clear bidding documents enable comparable and fair bids.

Q7.Prequalification is used to assess suppliers’ capability before:

Easy
A Inviting bids for certain procurements
B Paying every supplier
C Closing the department
D Issuing a pension
Bidding Documents PPSC 2024

Correct Answer: A

Prequalification identifies capable suppliers before bidding where appropriate.

Q8.Bid evaluation must be made against:

Medium
A The criteria stated in the bidding documents
B New criteria after opening
C Personal preference
D A media survey
Contract Award PPSC 2024

Correct Answer: A

Changing criteria after bid opening undermines fairness and transparency.

Q9.The successful bidder is generally the one whose bid is:

Medium
A Responsive and evaluated according to the stated criteria
B The most expensive without review
C Submitted after the deadline
D Missing required documents
Contract Award PPSC 2024

Correct Answer: A

Award follows responsiveness and evaluation under the stated criteria.

Q10.A bid submitted after the deadline is generally:

Easy
A Late and liable to rejection
B Automatically preferred
C Accepted secretly
D Evaluated first
Open Competitive Bidding PPSC 2024

Correct Answer: A

Late bids are generally rejected in accordance with the bidding documents.

Q11.A performance security protects the procuring agency against:

Easy
A Failure to perform the contract
B A candidate’s election loss
C A tax refund
D A leave application
Performance Security PPSC 2024

Correct Answer: A

Performance security protects against contractual non-performance.

Q12.Direct contracting should be used only when:

Medium
A The rules permit and justify it
B Competition is always inconvenient
C A supplier asks for it
D No record is needed
Direct Contracting PPSC 2024

Correct Answer: A

Direct contracting is an exception requiring rule-based justification.

Q13.Emergency procurement is intended for:

Medium
A Urgent situations where delay would harm the public interest
B Routine purchases every month
C Personal purchases
D Avoiding all documentation
Emergency Procurement PPSC 2024

Correct Answer: A

Emergency procedures address urgent public needs but still require accountability.

Q14.A contract should be awarded only after:

Easy
A Required evaluation and approval
B A verbal suggestion
C A supplier’s advertisement
D The contract is completed
Contract Award PPSC 2024

Correct Answer: A

Award follows evaluation and the required approval process.

Q15.Blacklisting is a measure that may be taken against a supplier for:

Medium
A Specified serious default or misconduct under the rules
B Submitting a valid bid
C Asking a question
D Attending a briefing
Blacklisting PPSC 2024

Correct Answer: A

Blacklisting requires rule-based grounds and due process.

Q16.A grievance redressal mechanism allows a bidder to:

Easy
A Challenge a procurement decision through the prescribed process
B Change the specification privately
C Choose the evaluation committee
D Avoid submitting a bid
Grievance Redressal PPSC 2024

Correct Answer: A

Grievance procedures provide a formal route for procurement complaints.

Q17.Transparency in procurement requires:

Easy
A Open, documented and understandable procedures
B Secret criteria
C Unrecorded negotiations
D Personal selection
Procurement Principles PPSC 2024

Correct Answer: A

Transparency requires clear and documented procurement processes.

Q18.A procuring agency should maintain procurement records for:

Easy
A Accountability and audit
B Destroying evidence
C Private advertising
D Avoiding competition
Procurement Principles PPSC 2024

Correct Answer: A

Records support accountability, review and audit.

Q19.A bid security is intended to discourage:

Medium
A Withdrawal or non-serious bidding
B Fair competition
C Proper documentation
D Technical evaluation
Bid Evaluation PPSC 2024

Correct Answer: A

Bid security protects the process against non-serious bidding conduct.